Ok, I have been hesitant to post an update on my studio situation because it has not been good. But here goes.
If you remember back we had quite a rainy spell. So things did not get started until way after I had wanted. Though there seemed to be plenty of times when the foundation could have been poured, it took forever.
Then it wasnt done correctly. It was very uneven. I didnt complain, just figured I was going to go with that "old world" stained concrete look anyway so no big deal. However... they did not set any anchor bolts to hold the structure in place on top of the foundation. But again, I thought no big deal. Now that I am in the place the uneven spots allow the rain to seep in along the edges and when sweeping the floor some of the "patches" they used to try and even out the worst spots are crumbly, found part of the paper bag that the cement mix was in protruding through the cement. Part of the foundation sticks out past the wall of the building so that when the rain hits the wall, it runs down, hits the foundation, then flows into the building. I can fix that with some flashing.
And that is just the foundation...
I drew up sketches and made notes etc. to make sure they knew I wanted a 2 story building, 2/3ds open all the way up, the other 3rd loft space towards the back. The unit is 16x20 and they used 2x6 to span the floor of the loft. Kind of a bouncy floor and not suitable. But I was under a lot of time constraints to get the thing done and again, figured it was no big deal I could double up the beams later. Then I looked out one day and realized they had put on the wrong roof. You could not have stood up at all in the loft area. I did make them take that off and start over. However the roof they did put on was uneven. I never really knew when they would show up, they said they would be there then didnt show. I would call and not get anyone, etc.
After they were "done" with the shell I was quite frustrated and didnt want to have anything to do with Better Bilt so hired some other people to do the insulation, sheetrock and electrical. When I started to look around thinking I might do the sheetrock myself even. I noticed that they had not done the corners of the building right. There was no way to hang sheetrock in many areas because there werent studs placed properly to do so, like double studs in the corner and along the ceiling/roofline. You could also see gaps in the outer siding where the siding and the walls didnt meet up right. The door was horribly crooked and not put in correctly. And I coud go on but thats enough.
It was a constant challenge of, what can I live with because I am on a time schedule and fix later, and what has to be fixed now. It still took longer in the end than it should have, and I know things like this do take longer, but this was absurd on many levels.
I got a person to come and give me an estimate on the sheetrock and he asked me where the building permit sticker was... I said. Well I was told that I had a building permit. I even remember writing a check specifically for that and annotating it for the building permit. I called the city and they had no permit for a building on my property.
I called Better Bilt and he said he was trying to get things done since I was on a tight schedule. I said, yes I am in a hurry, but I wanted things done legally. He said he would take care of it. By this time I wasnt going to wait on him or going to trust that he would do things right. I went down and got the information for what I would need to present. Luckily I was a drafting design and engineering student at Tulsa Vo Tech during my high school years and could draw up ,foundation and floor plans etc. Finally got that cleared up several weeks later. Boy was I crossing my fingers hoping it got approved and was in a location where it could be permitted lol.
I do want to say that I used Guidry Electric and they were great. Always answered the phone, came out when they said they were, had detailed contracts, and did a great job. Then there was the hassle with PSO and getting them out, those people were about to piss me off lol. I had the electrician do their first part before the sheetrock in August. PSO came and put an inspecion sticker on the meter box that is dated last of August. By the time the electrician showed back up to hang the lights and finish the electrical work after the sheetrock guy had finished, it was late September but PSO had still not connected the building to the grid. We called them and they gave us the run around saying there was no record of an inspection or request for service hook up. They said someone would come out within 6 days to hook it up, that most likely it would be sooner. I complained that it should have been done a month ago. They said there was nothing they could do about it and that they had no record. So I waited but by this time my "boss" for the large mural project was saying he was coming into town to inspect our progress. I needed to be in there. I had called several times during the week to see where things were and then on the 6th day I called and they said again, that they would be there sometime that week. I am sorry, but I lost it. I went off, and gosh they were stubborn. I wanted to talk to a manager or someone in charge, they said "They" dont talk to people. I asked where they were located, they said they didnt give out that info. I continued to yell and they argued back. They kept saying "Someone will be out there this week" I said, you said that the week before and it wasnt true and I HAVE to be in there! etc. etc. Finally I got really irate. Needless to say someone showed up within the hour and got my electricity hooked up. [
!]
I still have things that need to be done "no trim around the arched parts of the windows outside, the flashing around the foundation" outside needs to be painted,some inside trimwork etc. But at least I got in ther this last week. Fiiiinally
I was told the foundation and shell would take about a week to 2 weeks max plus about a week or two for sheetrock and electrical. Riiiiight.